January 24, 2025 SA Bianco Precast Adelaide Market Square Description of Work Performed:

During the work shift, tube filling was carried out in the following sectors:
1. East Lift:
• A total of 21 tubes were filled.
2. West Lift:
• A total of 7 tubes were filled.

Materials Used:
• A total of 31 bags were used for filling the tubes mentioned.

Conclusion:
The work was completed successfully, meeting the expected quantity of tubes to be filled in both lifts. All necessary materials were used efficiently.

32.00 VIEW PDF CSV

20713

January 23, 2025 SA United Precast UP1104 - 13 Metro Parade Level 1 and 2 7.50 VIEW PDF CSV

20712

January 23, 2025 QLD RCC Builders West End 11 Ferry Rd Level 4 and 8 8.00 VIEW PDF CSV

20711

January 22, 2025 QLD ADSEAL ADMIN Travel 1.00 VIEW PDF CSV

20710

January 23, 2025 SA Bianco Precast Adelaide Market Square Level 1 38.50 VIEW PDF CSV

20709

January 23, 2025 SA United Precast UP1161 - 23 Gray street, Adelaide Level 1 8.53 VIEW PDF CSV

20708

January 23, 2025 QLD ADSEAL ADMIN Site 1.50 VIEW PDF CSV

20707

January 23, 2025 SA United Precast UP1104 - 13 Metro Parade Interior caulking level 5 and stairs, following installation.
There is still plenty of caulking to be done.
8.00 VIEW PDF CSV

20706

January 23, 2025 QLD Peak Precast Ferny Grove 47 Conavalla street Ground floor 9.00 VIEW PDF CSV

20705

January 23, 2025 SA United Precast UP1197 - Xtracare - 75 Bacon st, Hindmarsh Internal caulking 8.00 VIEW PDF CSV

20704

January 22, 2025 QLD JKR Group Yatala 222 Stapylton Jacobs Well Rd - VISY Ground 11.50 VIEW PDF CSV

20703

January 22, 2025 SA Bianco Precast Adelaide Market Square Level 1. 24.00 VIEW PDF CSV

20702

January 22, 2025 QLD ADSEAL ADMIN Site and office 8.00 VIEW PDF CSV

20701

January 22, 2025 SA Hicrete Precast Systems Pty Ltd ANI - Naval Base Area: Ground floor where props were removed and exterior panels.
Task: Robert worked as a spotter and helped Angelo and Travis, fill in the tubes.
Material provided by the client: Antas Fireproof Fr
Task: Angelo worked until 8:45 doing caulking and then he worked as a patcher the remaining time, doing patcher on the boom and scissor.
16.00 VIEW PDF CSV

20700

January 22, 2025 QLD RCC Builders West End 11 Ferry Rd Level 3 and 4 8.00 VIEW PDF CSV