Row ID |
Date |
STATE |
Customer |
Job Site |
Location of Works | TTL LBR | View | CSV | |
---|---|---|---|---|---|---|---|---|---|
21796 |
May 27, 2025 | QLD | Paynters Pty Ltd | PO193949 - QRP0301 Caboolture Cancer Care | Site | 8.00 | VIEW | CSV | |
21795 |
May 27, 2025 | NSW | Forge outdoors Pty Ltd | PO030459 BRICK PIT RESERVE French Forest | Section 2 – flight 1 | 7.00 | VIEW | CSV | |
21794 |
May 27, 2025 | NSW | De Martin & Gasparini | 8-10 Lee Street Haymarket | Boa | 8.00 | VIEW | CSV | |
21793 |
May 26, 2025 | NSW | De Martin & Gasparini | 8-10 Lee Street Haymarket | Lower ground, B1 Mez, B1 | 8.00 | VIEW | CSV | |
21792 |
May 26, 2025 | QLD | BPG Constructions | Herston 51 Bramston Tce | Level 1 | 8.00 | VIEW | CSV | |
21791 |
May 26, 2025 | QLD | Novus Precast PTY LTD | Wellcamp 7 Vision Street | Site | 8.00 | VIEW | CSV | |
21790 |
May 26, 2025 | QLD | JKR Group | Yatala 222 Stapylton Jacobs Well Rd - VISY | Cullet building | 8.00 | VIEW | CSV | |
21789 |
May 26, 2025 | SA | United Precast | Bald Hills Road Mount Barker | Internal stair pool joints | 4.00 | VIEW | CSV | |
21788 |
May 26, 2025 | SA | Bert Farina Construction | 23 Adelphi Terrace, Glenelg North | Ground floor | 2.50 | VIEW | CSV | |
21787 |
May 26, 2025 | SA | Bianco Precast | Norwood Green - Osmond | 2nd level | 16.00 | VIEW | CSV | |
21786 |
May 26, 2025 | NSW | Forge outdoors Pty Ltd | PO030459 BRICK PIT RESERVE French Forest | Section 2 – flight 2 | 16.00 | VIEW | CSV | |
21785 |
May 26, 2025 | SA | Bianco Precast | Uniting - Bowden | Level 4. | 8.00 | VIEW | CSV | |
21784 |
May 26, 2025 | SA | Bert Farina Construction | 23 Adelphi Terrace, Glenelg North | Grount Floor | 4.00 | VIEW | CSV | |
21783 |
May 24, 2025 | SA | ADSEAL | ADMIN | Dropping off materials at the jobsite. Supporting the workers. |
1.00 | VIEW | CSV | |
21782 |
May 23, 2025 | SA | ADSEAL | ADMIN | Checking jobsites. Supporting the workers. Picking up and dropping off tools and materials. Organizing the roster. Meeting with a new customer. |
11.50 | VIEW | CSV |